Programme, delay & EOT

A real critical-path programme with a baseline that cannot be quietly re-cut, a four-week lookahead the site actually uses, and a delay register that builds the EOT case as it goes.

  • Planning engineer
  • Project manager
/ops/projects/[slug]/planning
Programme, delay & EOT — the screen inside ArgAssure

On a contractor's desk. An EOT claim lives or dies on whether the baseline was fixed and the delays were recorded contemporaneously. A programme re-baselined informally three times is not evidence of anything — which is why the baseline here is locked by the database, not by policy.

What it holds

WBS to critical path

Activities, logic, durations and float computed with cycle detection — a network that fails loudly if it is malformed rather than producing a confident wrong date.

Baseline immutability

Once published, the baseline is enforced as read-only at the database. A revision is a new baseline with a reason, and the variance is always measured against the one that was live.

Four-week lookahead and resources

A rolling lookahead generated from the programme, with resource and material-requirement schedules so procurement and manpower follow the plan rather than the panic.

Delay and EOT dossier

Events with cause, evidence, affected activities and computed impact on the critical path — assembled into an EOT submission with its programme analysis attached.

What it produces

  • Variance report against the live baseline
  • Schedule-quality checks before a programme is issued
  • EOT submission with the delay analysis and evidence index

What it will not allow

  • Editing a published baseline
  • A circular activity network
  • An EOT with no delay events behind it
Reads fromDPR (06) · Measurement (01) · Variations (03)

← All modules for this deskThe Contractor